Which of the following is an example of an excusable delay?

Prepare for the Back to Basic Certification Contracting Test. Study with comprehensive flashcards and multiple-choice questions, each with detailed explanations and insights. Enhance your knowledge and pass with confidence!

An example of an excusable delay is acts of the Government. This type of delay refers to circumstances that are beyond the control of the contractor and may impede their ability to complete the work within the specified timeframe. When governmental actions, such as changes in regulations, permitting delays, or other interventions made by public authorities, hinder progress, the contractor is typically granted additional time to fulfill their contractual obligations without penalties for exceeding the deadline.

In contrast, negligence by the contractor, failure to adhere to timelines, and supplier's operational issues generally do not qualify as excusable delays because they stem from the contractor's own actions or decisions or the actions of their suppliers, which could have been managed better. These types of delays are often considered non-excusable, leading to potential consequences such as penalties or contractual disputes. Understanding what constitutes excusable delays is critical in contract management, as it directly affects project timelines and obligations.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy